Have you wanted to quickly insert a new task within an existing task list in your project plan?
Tasks can be added anywhere within the existing task list.
View instructions for users of
If you are using Microsoft Project 2003/2007, to insert a new task within an existing task list:
1. Click on the task description below the desired insertion point.
2. Select New Task from the Insert menu or press the INSERT key.
3. Enter the task name , with ENTER or
to confirm.
4. Add the remaining tasks as shown below, to complete the task list:
TIP: New lines on tables are inserted ABOVE the cursor’s position.
If you are using Microsoft Project 2010, an alternative approach to inserting a new task is as follows:
1. Click on the task description below the desired insertion point:
2. On the Task tab, in the Insert group, click Task.
3. Creating a new task at the insertion point:
4. Overtype the name for the new task as Assemble and brief project team:
TIP: New lines on tables are inserted ABOVE the cursor’s position.